Parker Fluid Connector Group (FCG) has recently announced a material change to a another group of...
Shorter Lead Times for Selected Series of Parker Accumulators
Parker Cylinder & Accumulator Division announced decreased lead times for selected accumulator series, effective June 2024:
The lead time for the ACP08, ACP10, A3N/ A3E, A4N/A4E, A5N/A5E, and A6N/A6E series has been decreased from 28 to 24 weeks.
The lead time for the A7N/A7L, A8N/A8L, A9L, and A12L series has been decreased from 19 to 10 weeks.
In addition to the decreased lead times for the selected accumulator series, Parker Cylinder & Accumulator Division is also rolling out a new expedited repair service for customers with less than 20 pieces in need of servicing at their Santa Fe Springs, CA facility. With the lead time for repairs now reduced from 5 to just 2 weeks, customers can expect quicker turnaround times and minimal downtime for their equipment.
If you have any inquiries or need further information, do not hesitate to contact the knowledgeable Western Integrated Technology Sales Team.